BMC to wind up 24-hr water supply project
WATER & WASTE

BMC to wind up 24-hr water supply project

After facing inordinate delays, the Brihanmumbai Municipal Corporation (BMC) has decided to discontinue its Water Distribution Improvement Programme that was launched to provide round the clock water supply to Mumbai.

The Rs 275 crore programme was launched to improve water networks and phase wise beginning of 24 hour water supply in all areas.

According to BMC, contractor Suez Environment India Pvt Ltd filed for arbitration against the civic body. While only about 20% of project work has been completed, its five-year deadline had ended in July 2019. The corporation had given an extension of one year to the project, but the contractor had refused to continue.

BMC told the media that for 24 hours of uninterrupted supply, the contractor had asked BMC to provide about 30% additional water for the entire city. Currently, BMC supplies 3,900 million litres of water to Mumbai daily.


4th Indian Cement Review Conference 2021

17-18 March 

Click for event info


Since its inception, the project has been under the scanner for inordinate delays. While corporators have also raised the issue, last year, the Comptroller Auditor General (CAG) had rapped the BMC over the project's slow progress.

In these five years, as part of a pilot project, H West ward (Bandra, Khar Road and Santacruz) and T ward (Mulund) were to receive 24 hours water supply. To date, BMC has paid the contractor about Rs 47 crore for the executed work.

Under the project, the BMC had set a target of achieving 10 services, including geographic information system (GIS) mapping of all water networks, a survey of slum connections, quality assurance, consumer survey, setting up a call centre for consumers, asset registration and introduction of a leakage detection system.

Image source


After facing inordinate delays, the Brihanmumbai Municipal Corporation (BMC) has decided to discontinue its Water Distribution Improvement Programme that was launched to provide round the clock water supply to Mumbai. The Rs 275 crore programme was launched to improve water networks and phase wise beginning of 24 hour water supply in all areas. According to BMC, contractor Suez Environment India Pvt Ltd filed for arbitration against the civic body. While only about 20% of project work has been completed, its five-year deadline had ended in July 2019. The corporation had given an extension of one year to the project, but the contractor had refused to continue. BMC told the media that for 24 hours of uninterrupted supply, the contractor had asked BMC to provide about 30% additional water for the entire city. Currently, BMC supplies 3,900 million litres of water to Mumbai daily.4th Indian Cement Review Conference 202117-18 March Click for event info Since its inception, the project has been under the scanner for inordinate delays. While corporators have also raised the issue, last year, the Comptroller Auditor General (CAG) had rapped the BMC over the project's slow progress. In these five years, as part of a pilot project, H West ward (Bandra, Khar Road and Santacruz) and T ward (Mulund) were to receive 24 hours water supply. To date, BMC has paid the contractor about Rs 47 crore for the executed work. Under the project, the BMC had set a target of achieving 10 services, including geographic information system (GIS) mapping of all water networks, a survey of slum connections, quality assurance, consumer survey, setting up a call centre for consumers, asset registration and introduction of a leakage detection system. Image source

Next Story
Infrastructure Urban

USA Mortgage Rates Reach 6.95%

In July 2024, the average mortgage rate in the USA rose to 6.95%, marking a significant increase and impacting homebuyers nationwide. This upward trend in mortgage rates is attributed to several economic factors, including inflationary pressures, shifts in the Federal Reserve?s monetary policy, and broader market dynamics. The rise in mortgage rates presents challenges for potential homebuyers, making borrowing more expensive and potentially slowing down the housing market. Higher rates can lead to increased monthly payments for homeowners, reducing affordability and potentially deterring new ..

Next Story
Real Estate

Toronto Home Sales Increase 4.2%

In June 2024, home sales in Toronto experienced a notable rise, increasing by 4.2% compared to the previous month. This growth highlights a positive trend in the Toronto real estate market, indicating robust buyer activity and a favorable environment for sellers. Several factors contribute to this uptick, including attractive mortgage rates, strong demand for housing, and a stable economic backdrop. The Toronto Regional Real Estate Board (TRREB) reported this increase, pointing to heightened buyer confidence and competitive market conditions. Despite rising interest rates in other parts of Nor..

Next Story
Real Estate

New Zealand Boosts Home Construction

New Zealand is set to implement regulatory changes aimed at boosting home construction to address the nation's housing shortage. The government plans to streamline building consent processes, reduce construction costs, and increase the supply of affordable housing. This initiative is part of a broader strategy to make housing more accessible and alleviate the pressure on the housing market. Key elements of the regulatory overhaul include simplifying the approval process for new housing projects and reducing bureaucratic hurdles that often delay construction. By cutting red tape, the government..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram