Over 400 Mumbai infra projects hit by cost and time overruns
SMART CITIES

Over 400 Mumbai infra projects hit by cost and time overruns

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore.

All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement.

The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost.

During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs.

If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported.

Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months.

The reasons behind the time overruns:

  • Delay in tie-up for project financing
  • Delays in finalisation of detailed engineering
  • Change in scope
  • Delay in tendering
  • Ordering and equipment supply
  • Law and order issues
  • Delays in land acquisition
  • Delays in obtaining forest and environmental clearances
  • Lockdown in various states in the country

Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported.

Image Source

As many as 442 infrastructure projects in Mumbai, each worth Rs 150 crore or more, have taken a hit due to cost overruns of more than Rs 4.34 lakh crore. All infrastructure projects that are worth Rs 150 crore or more are monitored by the Ministry of Statistics and Programme Implementation. Of a total of 1,671 projects, nearly 442 witnessed cost overruns and 536 have suffered postponement. The total original cost of implementation of nearly 1,671 projects was calculated as Rs 21.21 lakh crore. The expected completion cost is Rs 25.56 lakh crore. It reflects the overall cost overruns of nearly Rs 4.34 lakh crore. It is 20.49% of its original cost. During November 2020, the expenditure incurred on these projects was Rs 11.94 lakh crore, which is 46.71% of the anticipated costs. If a delay is calculated based on the latest schedule of completion, then the number of delayed projects gets reduced to 412. For 942 projects, neither the year of commissioning nor the tentative gestation period has been reported. Of 536 delayed projects, close to 120 have an overall delta of 1-12 months. Whereas, 13 projects are likely to see 13-24 months. Also, 162 indicate delay for 25-60 months and nearly 120 reflect a delay of 61 months and more. Hence, the average time overrun for 536 delayed projects is 44.15 months. The reasons behind the time overruns: Delay in tie-up for project financing Delays in finalisation of detailed engineering Change in scope Delay in tendering Ordering and equipment supply Law and order issues Delays in land acquisition Delays in obtaining forest and environmental clearances Lockdown in various states in the country Various project agencies have not reported revisited cost estimates and commissioning schedules for projects. It indicates the time and cost overrun figures to be under-reported. Image Source

Next Story
Infrastructure Urban

USA Mortgage Rates Reach 6.95%

In July 2024, the average mortgage rate in the USA rose to 6.95%, marking a significant increase and impacting homebuyers nationwide. This upward trend in mortgage rates is attributed to several economic factors, including inflationary pressures, shifts in the Federal Reserve?s monetary policy, and broader market dynamics. The rise in mortgage rates presents challenges for potential homebuyers, making borrowing more expensive and potentially slowing down the housing market. Higher rates can lead to increased monthly payments for homeowners, reducing affordability and potentially deterring new ..

Next Story
Real Estate

Toronto Home Sales Increase 4.2%

In June 2024, home sales in Toronto experienced a notable rise, increasing by 4.2% compared to the previous month. This growth highlights a positive trend in the Toronto real estate market, indicating robust buyer activity and a favorable environment for sellers. Several factors contribute to this uptick, including attractive mortgage rates, strong demand for housing, and a stable economic backdrop. The Toronto Regional Real Estate Board (TRREB) reported this increase, pointing to heightened buyer confidence and competitive market conditions. Despite rising interest rates in other parts of Nor..

Next Story
Real Estate

New Zealand Boosts Home Construction

New Zealand is set to implement regulatory changes aimed at boosting home construction to address the nation's housing shortage. The government plans to streamline building consent processes, reduce construction costs, and increase the supply of affordable housing. This initiative is part of a broader strategy to make housing more accessible and alleviate the pressure on the housing market. Key elements of the regulatory overhaul include simplifying the approval process for new housing projects and reducing bureaucratic hurdles that often delay construction. By cutting red tape, the government..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram