90% of sewerage, infra work done in Smart City
SMART CITIES

90% of sewerage, infra work done in Smart City

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised.

In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish.

Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress.

Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Imagine Panaji Smart City Development Ltd (IPSCDL) announced that significant strides have been made in the sewerage and road infrastructure projects across Panaji, with completion rates reaching 90%. Notably, central Panaji, Fontainhas, Mala, and the Miramar-Caranzalem area stand out with completion rates of 99%, while St Inez and Ribandar closely follow at 97% and 96%, respectively. However, Altinho trails behind with 78% of its projects finalised. In central Panaji, IPSCDL has achieved the installation of 7.4km of sewerage pipeline, with 250 out of 251 manholes completed. Additionally, road infrastructure spanning 3.5km has been finished, with ongoing efforts for restoration. Similarly, St Inez has seen the completion of the entire 3km sewerage pipeline and 72 out of 75 manholes. Road construction is nearing completion, with just 150m left to finish. Ribandar boasts a fully installed 9.6km sewerage pipeline, complemented by the construction of 280 out of 300 manholes. Roadwork covering 4km has been accomplished, with restoration work on-going on a 1km stretch. Fontainhas reports the successful completion of a 2.2km sewerage pipeline project, along with all 73 manholes. Efforts are now focused on road restoration. In Mala, a 3.3km stretch of sewerage pipeline is fully operational, with 109 out of 110 manholes constructed. Road restoration efforts are also in progress. Similarly, in the Miramar-Caranzalem area, a 2.8km sewerage pipeline has been completed, along with 89 out of 90 manholes. Road restoration is actively underway. In Altinho, progress has been made on the sewerage pipeline project, with 450m laid, and 10 out of 18 manholes finished, while work continues on the rest. (Source: ET Infra)

Next Story
Resources

Mahindra selects ABB’s PixelPaint for premium paint options

ABB’s innovative PixelPaint technology has been selected by Mahindra & Mahindra (M&M), India’s leading SUV manufacturer, for its new electric vehicle paint facility. The technology, which uses an award-winning paint head similar to an inkjet printer, will begin serial production in 2025. “Our revolutionary PixelPaint technology can apply large areas of uniform color as well as the tiniest details with complete accuracy, without delaying the production line or the need for manual intervention,” said Joerg Reger, Managing Director of ABB Robotics Automotive Business Line. “By d..

Next Story
Infrastructure Transport

PJTL Lenders Approve Rs 10.20 billion One-Time Settlement

Lenders to the heavily indebted Panipat Jalandhar NH 1 Tollway (PJTL) have agreed to a one-time settlement for their Rs 34 billion dues. They accepted a Rs 10.20 billion all-cash offer from the promoters, the Canada-based Roadis Group and Hyderabad's Soma Enterprises, resulting in a 30% recovery, according to sources familiar with the deal. The account had been affected by farmers' agitation in the area for several years and was eventually declared a Non-Performing Asset (NPA). Several months ago, the National Asset Reconstruction Company (NARCL) had proposed to take over the debt, but the p..

Next Story
Infrastructure Urban

Capgemini to invest Rs 10 billion in new Chennai facility

Capgemini revealed plans to develop a new facility in Chennai, committing to invest approximately Rs 10 billion over the next three years. The IT and consulting services firm indicated that the 5,000-seat facility in Chennai is expected to be completed by April 2027. The campus will incorporate advanced energy and water-efficient technologies, utilize recycled materials, and implement rainwater harvesting during construction. Capgemini noted that the new facility is intended to become a prime destination for top-tier talent in southern India. It will be equipped with state-of-the-art IT in..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram