9 Bidders for Kanpur Metro Line-2’s KNPCC-11 Underground Work
RAILWAYS & METRO RAIL

9 Bidders for Kanpur Metro Line-2’s KNPCC-11 Underground Work

For Kanpur Metro's 8.6 kilometre Line-2, which will connect Rawatpur and Jaurali via 8 stations, 9 businesses—three of them in a consortium—have submitted bids.

Through three underground stations at Rawatpur, Kakadeo, and Double Pullia, the Kanpur Metro Phase 1 underground package, known as KNPCC-11, will link Agriculture Depot to Double Pullia Ramp.

In February 2023, the Uttar Pradesh Metro Rail Corporation (UPMRC) issued a request for proposals (RFP) for this contract, which had a Rs. 1025 crore budget and a 30-month timeframe.

Bidders

  • Afcons – SAM India JV
  • DRA – Soma JV
  • Hindustan Construction Company (HCC)
  • ITD Cementation
  • J Kumar Infraprojects (JKIL)
  • KPTL – Gulermak JV
  • Larsen & Toubro (L&T)
  • Shanghai Tunnel Engineering Co (STEC)
  • Tata Projects Ltd. (TPL)


    Package: KNPCC-11


    Brief Scope: Design and Construction of TBM Tunnel, Cut and Cover Tunnel, ramp after Double Pullia, ramps in Agriculture Depot for main line and depot connections and three underground metro stations (viz. Rawatpur, Kakadeo and Double Pullia) including Architectural finishes etc. on Corridor-2 of Kanpur MRTS Project at Kanpur, Uttar Pradesh, India india

    The cost of the Kanpur Metro project Phase 1 is estimated at around Rs 11,000 crore. Kanpur Metro Phase 1's DPR (Detailed Project Report) with 32.5 km of routes was prepared by Rail India Technical and Economic Service (RITES), approved by the State cabinet in March 2016 and by the Central Government's Cabinet in February 2019. The project is being financed through equity from the Government of India and the Government of Uttar Pradesh on an equal footing and through a EUR 650 million loan from the European Investment Bank (EIB) approved on July 15, 2020.

    Similar to the other 2 subterranean sections of Phase 1, UPMRC will probably call for the contractor for KNPCC-11 to use at least 2 tunnel boring machines (TBMs) to build 6 tunnels.

    This is the first of the city's Line-2's two civil packages. The building of an elevated bridge with 5 stations will be part of the other package from Double Pullia Ramp to Jaurali.

    After Package KNPCC-05 (given to Gulermak-SAM JV) and KNPCC-06 (granted to Afcons-SAM JV), both on 23.785 km Line-1 (IIT - Naubasta), this is the third underground stretch of the 32.38 km Kanpur Metro Phase 1 overall.

    About the project:
    Kanpur Metro rail was designed in 2016, with construction beginning in 2019. This public transportation service has been planned for the entire city and will be managed by the Uttar Pradesh Metro Rail Corporation Limited (UPMRCL). The active metro corridor currently extends 8.7 kilometers from Moti Jheel to IIT Kanpur. The Kanpur Metro route is being planned in stages. The first phase involves the development of an 8.7 km-long portion of the Orange Line, which is now operating, while the second phase includes the development of the remaining route as well as the Blue Line.

  • For Kanpur Metro's 8.6 kilometre Line-2, which will connect Rawatpur and Jaurali via 8 stations, 9 businesses—three of them in a consortium—have submitted bids. Through three underground stations at Rawatpur, Kakadeo, and Double Pullia, the Kanpur Metro Phase 1 underground package, known as KNPCC-11, will link Agriculture Depot to Double Pullia Ramp. In February 2023, the Uttar Pradesh Metro Rail Corporation (UPMRC) issued a request for proposals (RFP) for this contract, which had a Rs. 1025 crore budget and a 30-month timeframe. Bidders Afcons – SAM India JVDRA – Soma JVHindustan Construction Company (HCC)ITD CementationJ Kumar Infraprojects (JKIL)KPTL – Gulermak JVLarsen & Toubro (L&T)Shanghai Tunnel Engineering Co (STEC)Tata Projects Ltd. (TPL) Package: KNPCC-11 Brief Scope: Design and Construction of TBM Tunnel, Cut and Cover Tunnel, ramp after Double Pullia, ramps in Agriculture Depot for main line and depot connections and three underground metro stations (viz. Rawatpur, Kakadeo and Double Pullia) including Architectural finishes etc. on Corridor-2 of Kanpur MRTS Project at Kanpur, Uttar Pradesh, India india The cost of the Kanpur Metro project Phase 1 is estimated at around Rs 11,000 crore. Kanpur Metro Phase 1's DPR (Detailed Project Report) with 32.5 km of routes was prepared by Rail India Technical and Economic Service (RITES), approved by the State cabinet in March 2016 and by the Central Government's Cabinet in February 2019. The project is being financed through equity from the Government of India and the Government of Uttar Pradesh on an equal footing and through a EUR 650 million loan from the European Investment Bank (EIB) approved on July 15, 2020. Similar to the other 2 subterranean sections of Phase 1, UPMRC will probably call for the contractor for KNPCC-11 to use at least 2 tunnel boring machines (TBMs) to build 6 tunnels. This is the first of the city's Line-2's two civil packages. The building of an elevated bridge with 5 stations will be part of the other package from Double Pullia Ramp to Jaurali. After Package KNPCC-05 (given to Gulermak-SAM JV) and KNPCC-06 (granted to Afcons-SAM JV), both on 23.785 km Line-1 (IIT - Naubasta), this is the third underground stretch of the 32.38 km Kanpur Metro Phase 1 overall. About the project: Kanpur Metro rail was designed in 2016, with construction beginning in 2019. This public transportation service has been planned for the entire city and will be managed by the Uttar Pradesh Metro Rail Corporation Limited (UPMRCL). The active metro corridor currently extends 8.7 kilometers from Moti Jheel to IIT Kanpur. The Kanpur Metro route is being planned in stages. The first phase involves the development of an 8.7 km-long portion of the Orange Line, which is now operating, while the second phase includes the development of the remaining route as well as the Blue Line.

    Next Story
    Technology

    Step down your carbon footprint!

    The construction industry is a major contributor to global carbon emissions, accounting for a significant portion of the world's greenhouse gases (GHGs). Key materials like cement, steel, aggregates, and bitumen are primary sources of these emissions. As urbanisation continues to accelerate, especially in developing countries such as India, the environmental impact of construction activities is becoming increasingly severe. This situation necessitates the adoption of sustainable construction technologies to mitigate the carbon footprint associated with construction projects. Major contrib..

    Next Story
    Infrastructure Urban

    Wilo Mather aims 25% revenue from exports

    Wilo Mather and Platt Pumps, a leading manufacturer of pump solutions, is targeting to generate 25% of its revenue from exports over the next 2-3 years. This strategic goal underscores the company's commitment to expanding its global footprint and capitalising on growing international demand for high-quality pump systems. The company plans to leverage its strong engineering capabilities and innovative product portfolio to penetrate new markets and increase its share in existing ones. Wilo Mather and Platt Pumps aims to enhance its presence in regions such as the Middle East, Southeast Asia, an..

    Next Story
    Infrastructure Urban

    Adani Group to raise up to $3 billion in equity

    Adani Group has unveiled plans to invest a staggering ?1.3 trillion in the fiscal year 2025, alongside raising up to $3 billion in equity. This ambitious investment strategy is set to fuel the conglomerate's diverse growth initiatives across multiple sectors, including energy, infrastructure, and logistics. The ?1.3 trillion investment will be allocated to expanding Adani Group's presence in renewable energy, enhancing port capacities, and developing cutting-edge infrastructure projects. These investments aim to bolster India's economic growth, create jobs, and promote sustainable development...

    Hi There!

    Now get regular updates from CW Magazine on WhatsApp!

    Click on link below, message us with a simple hi, and SAVE our number

    You will have subscribed to our Construction News on Whatsapp! Enjoy

    +91 81086 03000

    Join us Telegram