Road structures can necessitate horizontal and vertical formwork
We opted for a customised cribs formwork for the in-situ concrete because this formwork suited the site conditions both technically and economically, says Sachin More, Head, Formwork, JMC Projects (In
ROADS & HIGHWAYS

Road structures can necessitate horizontal and vertical formwork

Road construction necessitates formwork for retaining walls, culverts, tunnels and flyovers (in-situ obligatory span or precast segments). The type of structure is the foremost factor influencing the choice of formwork. “Other factors influencing the choice of formwork are desired finish, site safety needs, targeted cycle times, availability, repetitions needed, weight of the formwork and handling ability, whether single use or multipurpose, repairs and maintenance costs, training cost and client specifications,” says Sachin More, Head, Formwork, JMC Projects (India).

When JMC Projects (India) started to implement the Mankhurd flyover project, the structural design majorly influenced the choice of formwork. The horizontal parts of the flyover were to be built with precast segments in some sections and in-situ concrete in others. The formwork had to be chosen accordingly.

“We opted for a customised cribs formwork for the in-situ concrete because this formwork suited the site conditions both technically and economically,” explains More. “We had to work in a confined area with ongoing traffic, so using cribs allowed us greater spans for passing traffic. Cribs formwork can be easily erected and dismantled with the help of a crane and supports a greater slab thickness. There could have been several other options like as deck, shoring or flex formwork; however, we preferred to use our own asset bank.”

“For precast segments, custom-made formwork in mild steel is suitable and can be designed as per the desired loading conditions unlike modular panels,” adds More. “This formwork has a two to three-day cycle; it is easy to align and gives the desired finish. It can be best handled with hydraulic systems. As we had to separately cast the peir (column) and the peir cap because of the large size, we needed separate vertical formwork for these elements.” Custom-made formwork in mild steel, which supports greater loads/pressured, was preferred over other modular formwork. This had a two to three-day cycle and necessitated the use of a crane.

JMC Projects (India) fabricated all this formwork itself.

CHARU BAHRI

Road construction necessitates formwork for retaining walls, culverts, tunnels and flyovers (in-situ obligatory span or precast segments). The type of structure is the foremost factor influencing the choice of formwork. “Other factors influencing the choice of formwork are desired finish, site safety needs, targeted cycle times, availability, repetitions needed, weight of the formwork and handling ability, whether single use or multipurpose, repairs and maintenance costs, training cost and client specifications,” says Sachin More, Head, Formwork, JMC Projects (India). When JMC Projects (India) started to implement the Mankhurd flyover project, the structural design majorly influenced the choice of formwork. The horizontal parts of the flyover were to be built with precast segments in some sections and in-situ concrete in others. The formwork had to be chosen accordingly. “We opted for a customised cribs formwork for the in-situ concrete because this formwork suited the site conditions both technically and economically,” explains More. “We had to work in a confined area with ongoing traffic, so using cribs allowed us greater spans for passing traffic. Cribs formwork can be easily erected and dismantled with the help of a crane and supports a greater slab thickness. There could have been several other options like as deck, shoring or flex formwork; however, we preferred to use our own asset bank.” “For precast segments, custom-made formwork in mild steel is suitable and can be designed as per the desired loading conditions unlike modular panels,” adds More. “This formwork has a two to three-day cycle; it is easy to align and gives the desired finish. It can be best handled with hydraulic systems. As we had to separately cast the peir (column) and the peir cap because of the large size, we needed separate vertical formwork for these elements.” Custom-made formwork in mild steel, which supports greater loads/pressured, was preferred over other modular formwork. This had a two to three-day cycle and necessitated the use of a crane. JMC Projects (India) fabricated all this formwork itself. CHARU BAHRI

Next Story
Infrastructure Urban

USA Mortgage Rates Reach 6.95%

In July 2024, the average mortgage rate in the USA rose to 6.95%, marking a significant increase and impacting homebuyers nationwide. This upward trend in mortgage rates is attributed to several economic factors, including inflationary pressures, shifts in the Federal Reserve?s monetary policy, and broader market dynamics. The rise in mortgage rates presents challenges for potential homebuyers, making borrowing more expensive and potentially slowing down the housing market. Higher rates can lead to increased monthly payments for homeowners, reducing affordability and potentially deterring new ..

Next Story
Real Estate

Toronto Home Sales Increase 4.2%

In June 2024, home sales in Toronto experienced a notable rise, increasing by 4.2% compared to the previous month. This growth highlights a positive trend in the Toronto real estate market, indicating robust buyer activity and a favorable environment for sellers. Several factors contribute to this uptick, including attractive mortgage rates, strong demand for housing, and a stable economic backdrop. The Toronto Regional Real Estate Board (TRREB) reported this increase, pointing to heightened buyer confidence and competitive market conditions. Despite rising interest rates in other parts of Nor..

Next Story
Real Estate

New Zealand Boosts Home Construction

New Zealand is set to implement regulatory changes aimed at boosting home construction to address the nation's housing shortage. The government plans to streamline building consent processes, reduce construction costs, and increase the supply of affordable housing. This initiative is part of a broader strategy to make housing more accessible and alleviate the pressure on the housing market. Key elements of the regulatory overhaul include simplifying the approval process for new housing projects and reducing bureaucratic hurdles that often delay construction. By cutting red tape, the government..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram