CRZ clearance cancellation for Mumbai Coastal Road to impact L&T, HCC order books
The proposed 29.2-km Mumbai coastal road project would connect the Marine Drive area of south Mumbai to suburban Borivali in the north.
ROADS & HIGHWAYS

CRZ clearance cancellation for Mumbai Coastal Road to impact L&T, HCC order books

The Bombay High Court recently cancelled the coastal regulation zone (CRZ) clearances granted to the ambitious Rs 140-billion Mumbai Coastal Road Project, reasoning that there was serious lacuna in the decision-making process and lack of proper scientific study. The decision is likely to impact the order book of large construction players such as Larsen & Toubro (L&T) and HCC, who are involved in the construction of the project.

L&T’s total order book stood at Rs 2.93 trillion, while HCC’s order book at Rs 185.54 billion, as on March 2019. While L&T has been awarded two packages of the project worth Rs 74.89 billion; HCC, in a JV with Hyundai Development Corporation, has been awarded another contract worth Rs 21.26 billion. The Mumbai Coastal Road project has so far witnessed only preliminary works in terms of execution. And, notably, in the case of a delay in clearances or a lack of them, the order books of both these companies are likely to be impacted.

The High Court reportedly stated: “We declare that MCGM (Municipal Corporation of Greater Mumbai) cannot proceed with the works without obtaining an environmental clearance under the environmental impact assessment (EIA) notification. Further, permission under the Wildlife (Protection) Act, 1972, should also be obtained.” Further, as reported, the High Court noted that the environmental clearance was required to be taken by the BMC under the EIA notification issued by the Centre.

The proposed 29.2-km Mumbai coastal road project would connect the Marine Drive area of south Mumbai to suburban Borivali in the north.

The Bombay High Court recently cancelled the coastal regulation zone (CRZ) clearances granted to the ambitious Rs 140-billion Mumbai Coastal Road Project, reasoning that there was serious lacuna in the decision-making process and lack of proper scientific study. The decision is likely to impact the order book of large construction players such as Larsen & Toubro (L&T) and HCC, who are involved in the construction of the project.L&T’s total order book stood at Rs 2.93 trillion, while HCC’s order book at Rs 185.54 billion, as on March 2019. While L&T has been awarded two packages of the project worth Rs 74.89 billion; HCC, in a JV with Hyundai Development Corporation, has been awarded another contract worth Rs 21.26 billion. The Mumbai Coastal Road project has so far witnessed only preliminary works in terms of execution. And, notably, in the case of a delay in clearances or a lack of them, the order books of both these companies are likely to be impacted.The High Court reportedly stated: “We declare that MCGM (Municipal Corporation of Greater Mumbai) cannot proceed with the works without obtaining an environmental clearance under the environmental impact assessment (EIA) notification. Further, permission under the Wildlife (Protection) Act, 1972, should also be obtained.” Further, as reported, the High Court noted that the environmental clearance was required to be taken by the BMC under the EIA notification issued by the Centre.The proposed 29.2-km Mumbai coastal road project would connect the Marine Drive area of south Mumbai to suburban Borivali in the north.

Next Story
Infrastructure Urban

USA Mortgage Rates Reach 6.95%

In July 2024, the average mortgage rate in the USA rose to 6.95%, marking a significant increase and impacting homebuyers nationwide. This upward trend in mortgage rates is attributed to several economic factors, including inflationary pressures, shifts in the Federal Reserve?s monetary policy, and broader market dynamics. The rise in mortgage rates presents challenges for potential homebuyers, making borrowing more expensive and potentially slowing down the housing market. Higher rates can lead to increased monthly payments for homeowners, reducing affordability and potentially deterring new ..

Next Story
Real Estate

Toronto Home Sales Increase 4.2%

In June 2024, home sales in Toronto experienced a notable rise, increasing by 4.2% compared to the previous month. This growth highlights a positive trend in the Toronto real estate market, indicating robust buyer activity and a favorable environment for sellers. Several factors contribute to this uptick, including attractive mortgage rates, strong demand for housing, and a stable economic backdrop. The Toronto Regional Real Estate Board (TRREB) reported this increase, pointing to heightened buyer confidence and competitive market conditions. Despite rising interest rates in other parts of Nor..

Next Story
Real Estate

New Zealand Boosts Home Construction

New Zealand is set to implement regulatory changes aimed at boosting home construction to address the nation's housing shortage. The government plans to streamline building consent processes, reduce construction costs, and increase the supply of affordable housing. This initiative is part of a broader strategy to make housing more accessible and alleviate the pressure on the housing market. Key elements of the regulatory overhaul include simplifying the approval process for new housing projects and reducing bureaucratic hurdles that often delay construction. By cutting red tape, the government..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram