Afcons wins Mumbai-Ahmedabad Bullet Train’s C2 Tunnel Contract
ROADS & HIGHWAYS

Afcons wins Mumbai-Ahmedabad Bullet Train’s C2 Tunnel Contract

The National High-Speed Rail Corporation Ltd. (NHSRCL) of India and Afcons Infrastructure signed an Rs. 6397.27 crore contract on Thursday for the construction of the 20.377 km subterranean Package C-2 of the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train).

Package C2 of the main line will consist of a roughly 3 km "undersea" tunnel through Thane Creek and will connect chainage Km 0.773 (Bandra Kurla Complex Station) to Km 21.150 (Shilphata Ramp).

Afcons Infrastructure is attempting to meet a target of 1888 days (5.17 years) and will be required to use at least three Mega Tunnel Boring Machines (TBMs) with a diameter of around 14.5 meters to bore approximately 16 kilometers of the tunnel. The next 5 kilometers will be constructed utilizing the New Austrian Tunneling Method (NATM).

Afcons was designated the lowest bidder for C2's contract in early April 2023, narrowly defeating Larsen & Toubro, and NHSCRL gave a Letter of Acceptance (LoA) to Afcons in mid-May 2023.

MAHSR-C-2 is the IFB number for this package.

Brief Scope: Construction of Tunnelling Works, including Testing and Commissioning, for a Double Line High-Speed Railway between Mumbai Underground Station at Bandra-Kurla Complex (MAHSR Km. 0.773) and Shilphata (MAHSR Km. 21.150) using (TBM) and (NATM).

Afcons will build three shafts at BKC Station, Vikhroli, and Sawli at depths of 36m, 56m, and 39m, respectively, to launch and retrieve three TBMs. NATM tunneling will be facilitated by a 42m inclined shaft at Ghansoli and a tunnel entrance at Shilphata.

With this development, Afcons will most likely begin basic preparatory work by the end of the month, building work by the end of Q3 2023, and actual tunneling work no earlier than Q1 2025.

135.45 km Package C3 (Shilphata - Zaroli) in Maharashtra is the only civil package still open for bidding. NHSRCL is now evaluating technical bids submitted in April from four firms.

The National High-Speed Rail Corporation Ltd. (NHSRCL) of India and Afcons Infrastructure signed an Rs. 6397.27 crore contract on Thursday for the construction of the 20.377 km subterranean Package C-2 of the 508.17 km Mumbai-Ahmedabad High-Speed Rail (MAHSR Bullet Train). Package C2 of the main line will consist of a roughly 3 km undersea tunnel through Thane Creek and will connect chainage Km 0.773 (Bandra Kurla Complex Station) to Km 21.150 (Shilphata Ramp). Afcons Infrastructure is attempting to meet a target of 1888 days (5.17 years) and will be required to use at least three Mega Tunnel Boring Machines (TBMs) with a diameter of around 14.5 meters to bore approximately 16 kilometers of the tunnel. The next 5 kilometers will be constructed utilizing the New Austrian Tunneling Method (NATM). Afcons was designated the lowest bidder for C2's contract in early April 2023, narrowly defeating Larsen & Toubro, and NHSCRL gave a Letter of Acceptance (LoA) to Afcons in mid-May 2023. MAHSR-C-2 is the IFB number for this package. Brief Scope: Construction of Tunnelling Works, including Testing and Commissioning, for a Double Line High-Speed Railway between Mumbai Underground Station at Bandra-Kurla Complex (MAHSR Km. 0.773) and Shilphata (MAHSR Km. 21.150) using (TBM) and (NATM). Afcons will build three shafts at BKC Station, Vikhroli, and Sawli at depths of 36m, 56m, and 39m, respectively, to launch and retrieve three TBMs. NATM tunneling will be facilitated by a 42m inclined shaft at Ghansoli and a tunnel entrance at Shilphata. With this development, Afcons will most likely begin basic preparatory work by the end of the month, building work by the end of Q3 2023, and actual tunneling work no earlier than Q1 2025. 135.45 km Package C3 (Shilphata - Zaroli) in Maharashtra is the only civil package still open for bidding. NHSRCL is now evaluating technical bids submitted in April from four firms.

Next Story
Resources

Mahindra selects ABB’s PixelPaint for premium paint options

ABB’s innovative PixelPaint technology has been selected by Mahindra & Mahindra (M&M), India’s leading SUV manufacturer, for its new electric vehicle paint facility. The technology, which uses an award-winning paint head similar to an inkjet printer, will begin serial production in 2025. “Our revolutionary PixelPaint technology can apply large areas of uniform color as well as the tiniest details with complete accuracy, without delaying the production line or the need for manual intervention,” said Joerg Reger, Managing Director of ABB Robotics Automotive Business Line. “By d..

Next Story
Infrastructure Transport

PJTL Lenders Approve Rs 10.20 billion One-Time Settlement

Lenders to the heavily indebted Panipat Jalandhar NH 1 Tollway (PJTL) have agreed to a one-time settlement for their Rs 34 billion dues. They accepted a Rs 10.20 billion all-cash offer from the promoters, the Canada-based Roadis Group and Hyderabad's Soma Enterprises, resulting in a 30% recovery, according to sources familiar with the deal. The account had been affected by farmers' agitation in the area for several years and was eventually declared a Non-Performing Asset (NPA). Several months ago, the National Asset Reconstruction Company (NARCL) had proposed to take over the debt, but the p..

Next Story
Infrastructure Urban

Capgemini to invest Rs 10 billion in new Chennai facility

Capgemini revealed plans to develop a new facility in Chennai, committing to invest approximately Rs 10 billion over the next three years. The IT and consulting services firm indicated that the 5,000-seat facility in Chennai is expected to be completed by April 2027. The campus will incorporate advanced energy and water-efficient technologies, utilize recycled materials, and implement rainwater harvesting during construction. Capgemini noted that the new facility is intended to become a prime destination for top-tier talent in southern India. It will be equipped with state-of-the-art IT in..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram