NHAI: Virudhunagar-Kanyakumari stretch re-laying to begin in May
ROADS & HIGHWAYS

NHAI: Virudhunagar-Kanyakumari stretch re-laying to begin in May

The National Highways Authority of India (NHAI) said the overlaying work of the 180 km Virudhunagar-Kanyakumari four lane national highway is likely to begin at the start of May and will likely be completed by October 20.

According to NHAI, milling could be planned for 1.5 km a day, whereas relaying could be done only for 1.2 km a day. NHAI said that work on studs, thermoplastic painting and road furniture is also planned.

The authority was replying to a Right to Information (RTI) question by R Pandiaraja. On questions pertaining to improving the green cover along the national highway, NHAI stated that it has targeted to plant 583 trees every kilometre, subject to the availability of vacant spaces. There is no plan to plant trees on the median.

Pandiaraja said NHAI and the contractors concerned for the maintenance of the sections of NH 44 between Virudhunagar and Kanyakumari should make use of the night lockdown and other restrictions on the movement of vehicles in view of curtailing the second wave of Covid-19 to expedite and complete relaying work as soon as possible.

The activist also stressed on the implementation of adequate safety measures and placement of proper signboards to indicate that work is in progress to avert accidents on the busy highway in case of diversions.

Image Source


Also read: Economic corridors: ADB approves Rs 3.5k cr loan for TN project

The National Highways Authority of India (NHAI) said the overlaying work of the 180 km Virudhunagar-Kanyakumari four lane national highway is likely to begin at the start of May and will likely be completed by October 20. According to NHAI, milling could be planned for 1.5 km a day, whereas relaying could be done only for 1.2 km a day. NHAI said that work on studs, thermoplastic painting and road furniture is also planned. The authority was replying to a Right to Information (RTI) question by R Pandiaraja. On questions pertaining to improving the green cover along the national highway, NHAI stated that it has targeted to plant 583 trees every kilometre, subject to the availability of vacant spaces. There is no plan to plant trees on the median. Pandiaraja said NHAI and the contractors concerned for the maintenance of the sections of NH 44 between Virudhunagar and Kanyakumari should make use of the night lockdown and other restrictions on the movement of vehicles in view of curtailing the second wave of Covid-19 to expedite and complete relaying work as soon as possible. The activist also stressed on the implementation of adequate safety measures and placement of proper signboards to indicate that work is in progress to avert accidents on the busy highway in case of diversions. Image Source Also read: Economic corridors: ADB approves Rs 3.5k cr loan for TN project

Next Story
Infrastructure Urban

USA Mortgage Rates Reach 6.95%

In July 2024, the average mortgage rate in the USA rose to 6.95%, marking a significant increase and impacting homebuyers nationwide. This upward trend in mortgage rates is attributed to several economic factors, including inflationary pressures, shifts in the Federal Reserve?s monetary policy, and broader market dynamics. The rise in mortgage rates presents challenges for potential homebuyers, making borrowing more expensive and potentially slowing down the housing market. Higher rates can lead to increased monthly payments for homeowners, reducing affordability and potentially deterring new ..

Next Story
Real Estate

Toronto Home Sales Increase 4.2%

In June 2024, home sales in Toronto experienced a notable rise, increasing by 4.2% compared to the previous month. This growth highlights a positive trend in the Toronto real estate market, indicating robust buyer activity and a favorable environment for sellers. Several factors contribute to this uptick, including attractive mortgage rates, strong demand for housing, and a stable economic backdrop. The Toronto Regional Real Estate Board (TRREB) reported this increase, pointing to heightened buyer confidence and competitive market conditions. Despite rising interest rates in other parts of Nor..

Next Story
Real Estate

New Zealand Boosts Home Construction

New Zealand is set to implement regulatory changes aimed at boosting home construction to address the nation's housing shortage. The government plans to streamline building consent processes, reduce construction costs, and increase the supply of affordable housing. This initiative is part of a broader strategy to make housing more accessible and alleviate the pressure on the housing market. Key elements of the regulatory overhaul include simplifying the approval process for new housing projects and reducing bureaucratic hurdles that often delay construction. By cutting red tape, the government..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram