373 projects show cost overruns of Rs 3.89 trillion
As many as?373?infrastructure?projects, each worth?Rs?150 crore or more, are hit by?cost overruns?of more than?Rs 3.89?lakh crore owing to delays and other reasons, according to a report.?
ECONOMY & POLICY

373 projects show cost overruns of Rs 3.89 trillion

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion.

The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects.

Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months.

Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported.

Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

The Ministry of Statistics and Programme Implementation (MoSPI), charged with the responsibility of monitoring infrastructure projects worth Rs 1.5 billion or more, has released a report for August 2019, according to which, out of a total 1,634 projects, around 373 have shown cost overruns to the tune of Rs 3.89 trillion. The report states that the original estimated cost of all the projects is approximately Rs 19.40 trillion. Completion cost is now expected to be around Rs 23.29 trillion. This amounts to cost overruns of around 20.05 per cent from the original cost – of around Rs 3.89 trillion. Till August 2019, the expenses incurred by these projects amounts to Rs 9.75 trillion, which is 41.85 per cent of the expected cost of the projects. Additionally, the report included the number of projects that had crossed their deadlines; these amounted to 552. The average time overrun for all 552 projects was reported to be 38.89 months. Reportedly, out of all the 552 projects showing time overruns, 181 projects are showing an overall delay in the range of 1 to 12 months, 128 projects have delay of 13 to 24 months, 127 projects show delay in the range of 25 to 60 months and 116 projects reflect delay of 61 months and above. However, as per the report, the number of delayed projects decreases to 489 if the delay is calculated on the basis of latest schedule of completion. Moreover, for 687 projects neither the year of commissioning nor the tentative gestation period has been reported. Escalations in time could be caused by issues relating to obtaining forest clearances, acquiring required land and supply of equipment. According to the report, developers also face additional constraints because of funding, geographical conditions, labour issues and court cases, among other reasons. Reportedly, it is possible that the time and cost overrun figures have been under-reported since project agencies have not reported revised cost estimates and commissioning schedules for numerous projects.

Next Story
Infrastructure Urban

USA Mortgage Rates Reach 6.95%

In July 2024, the average mortgage rate in the USA rose to 6.95%, marking a significant increase and impacting homebuyers nationwide. This upward trend in mortgage rates is attributed to several economic factors, including inflationary pressures, shifts in the Federal Reserve?s monetary policy, and broader market dynamics. The rise in mortgage rates presents challenges for potential homebuyers, making borrowing more expensive and potentially slowing down the housing market. Higher rates can lead to increased monthly payments for homeowners, reducing affordability and potentially deterring new ..

Next Story
Real Estate

Toronto Home Sales Increase 4.2%

In June 2024, home sales in Toronto experienced a notable rise, increasing by 4.2% compared to the previous month. This growth highlights a positive trend in the Toronto real estate market, indicating robust buyer activity and a favorable environment for sellers. Several factors contribute to this uptick, including attractive mortgage rates, strong demand for housing, and a stable economic backdrop. The Toronto Regional Real Estate Board (TRREB) reported this increase, pointing to heightened buyer confidence and competitive market conditions. Despite rising interest rates in other parts of Nor..

Next Story
Real Estate

New Zealand Boosts Home Construction

New Zealand is set to implement regulatory changes aimed at boosting home construction to address the nation's housing shortage. The government plans to streamline building consent processes, reduce construction costs, and increase the supply of affordable housing. This initiative is part of a broader strategy to make housing more accessible and alleviate the pressure on the housing market. Key elements of the regulatory overhaul include simplifying the approval process for new housing projects and reducing bureaucratic hurdles that often delay construction. By cutting red tape, the government..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram