Slipforms for hydropower projects
HCC opted for slipforms for the concreting of a 115-m-deep surge shaft for the Punatsangchhu hydropower project Stage I, a 1,200-mw, run-of-the-river project in Western Bhutan.
POWER & RENEWABLE ENERGY

Slipforms for hydropower projects

HCC opted for slipforms for the concreting of a 115-m-deep surge shaft for the Punatsangchhu hydropower project Stage I, a 1,200-mw, run-of-the-river project in Western Bhutan.

“We opted for slip-forming because it enables continuous, non-interrupted, cast-in-place jointless concrete structures that have superior performance characteristics compared to piece-wise construction using discrete form elements,” says S D Jeur, Senior Vice-President, Projects, HCC.

Slipforms with a three-layered platform structure were used. The entire formwork structure was built in-house. The top platform was used to erect the reinforcement concrete, the middle platform was used for general movement, and the bottom one was used to provide the finishing to the concrete surface.

Slipforms have to be in a continuous motion so that the concrete does not stick to them. The speed of this formwork depends on several factors like the weather condition, the amount of concrete poured at a time and the size of the structure. As the slipform can move (slipping rate, usually between 5 and 30 cm/hour) whenever the concrete can carry the load of its weight in the lowest parts of form sheet, the likely concrete setting time was determined based on the weather conditions (temperature, humidity, etc), cement ratio, type of cement, slump and admixtures.

Usually, the slipform structure rises up with the daily progress of 0.75 m/day in standard conditions. However, at Punatsangchhu-I HEP, the daily progress harnessed from slipform was at an average of 1 m/day. The concrete lining thickness varied from 850 mm at the top, 1,200 mm in the middle and 1,500 mm at the bottom. Concrete was poured into the forms in layers of about 200 mm.

CHARU BAHRI

HCC opted for slipforms for the concreting of a 115-m-deep surge shaft for the Punatsangchhu hydropower project Stage I, a 1,200-mw, run-of-the-river project in Western Bhutan. “We opted for slip-forming because it enables continuous, non-interrupted, cast-in-place jointless concrete structures that have superior performance characteristics compared to piece-wise construction using discrete form elements,” says S D Jeur, Senior Vice-President, Projects, HCC. Slipforms with a three-layered platform structure were used. The entire formwork structure was built in-house. The top platform was used to erect the reinforcement concrete, the middle platform was used for general movement, and the bottom one was used to provide the finishing to the concrete surface. Slipforms have to be in a continuous motion so that the concrete does not stick to them. The speed of this formwork depends on several factors like the weather condition, the amount of concrete poured at a time and the size of the structure. As the slipform can move (slipping rate, usually between 5 and 30 cm/hour) whenever the concrete can carry the load of its weight in the lowest parts of form sheet, the likely concrete setting time was determined based on the weather conditions (temperature, humidity, etc), cement ratio, type of cement, slump and admixtures. Usually, the slipform structure rises up with the daily progress of 0.75 m/day in standard conditions. However, at Punatsangchhu-I HEP, the daily progress harnessed from slipform was at an average of 1 m/day. The concrete lining thickness varied from 850 mm at the top, 1,200 mm in the middle and 1,500 mm at the bottom. Concrete was poured into the forms in layers of about 200 mm. CHARU BAHRI

Next Story
Resources

Mahindra selects ABB’s PixelPaint for premium paint options

ABB’s innovative PixelPaint technology has been selected by Mahindra & Mahindra (M&M), India’s leading SUV manufacturer, for its new electric vehicle paint facility. The technology, which uses an award-winning paint head similar to an inkjet printer, will begin serial production in 2025. “Our revolutionary PixelPaint technology can apply large areas of uniform color as well as the tiniest details with complete accuracy, without delaying the production line or the need for manual intervention,” said Joerg Reger, Managing Director of ABB Robotics Automotive Business Line. “By d..

Next Story
Infrastructure Transport

PJTL Lenders Approve Rs 10.20 billion One-Time Settlement

Lenders to the heavily indebted Panipat Jalandhar NH 1 Tollway (PJTL) have agreed to a one-time settlement for their Rs 34 billion dues. They accepted a Rs 10.20 billion all-cash offer from the promoters, the Canada-based Roadis Group and Hyderabad's Soma Enterprises, resulting in a 30% recovery, according to sources familiar with the deal. The account had been affected by farmers' agitation in the area for several years and was eventually declared a Non-Performing Asset (NPA). Several months ago, the National Asset Reconstruction Company (NARCL) had proposed to take over the debt, but the p..

Next Story
Infrastructure Urban

Capgemini to invest Rs 10 billion in new Chennai facility

Capgemini revealed plans to develop a new facility in Chennai, committing to invest approximately Rs 10 billion over the next three years. The IT and consulting services firm indicated that the 5,000-seat facility in Chennai is expected to be completed by April 2027. The campus will incorporate advanced energy and water-efficient technologies, utilize recycled materials, and implement rainwater harvesting during construction. Capgemini noted that the new facility is intended to become a prime destination for top-tier talent in southern India. It will be equipped with state-of-the-art IT in..

Hi There!

Now get regular updates from CW Magazine on WhatsApp!

Click on link below, message us with a simple hi, and SAVE our number

You will have subscribed to our Construction News on Whatsapp! Enjoy

+91 81086 03000

Join us Telegram